Driveway and Road Restoration

*Attention Residents of 1st Ave between 6th  and 11th  street*

Wastewater system rehabilitation work started in the fall of 2021 and will continue this spring. This section of line will be completed and residents who are connected to the system will be commissioned and operating on the wastewater system this spring.

This section of the system is a test section that will run over the winter of 2022-2023 to confirm that everything is operating as designed. Because this is a test section, and there is a possibility that there may be some additional rehabilitation required on the line, the restoration/paving of roads and driveways will not be completed in 2022.

THS will restore your driveway to a compacted gravel surface, however they have been advised that Council wishes to defer any additional work such as paving or bricks until 2023 to avoid any re-work if repairs on the wastewater line become necessary.  Council will provide additional information regarding the timing and Summer Village involvement to affected residents in 2023.